Alliance Machine Systems International, LLC
NewsContactCompanyServiceConferenceAffiliatesHome

Products

Specialty
Folder Gluers

Robotics

Prefeeders

Counter Ejectors


RDC Stackers

Bundle Breakers
& Separators

Bundle Handlers


Load Formers
& Palletizers

Pallet Handlers


Stack Handlers


Glue Prep Systems

Special Equipment

  

SERVICE BULLETIN

Bulletin: SVB-105

Date Issued: April 2, 2004

Category: Assembly

Subject: Lift Assembly Double Chain Sprocket Inspection

Machine Models: All TEI Jumbo Bottom Feeders and Jumbo Top Feeders from P4200 to P10840

Back to Index
 
Problem Recommended Action Procedure

Problem:

An operator of a Jumbo Bottom Feeder recently reported finding unexpected structural damage that required significant unscheduled machine downtime to repair. No indications of an impending problem were evident until maintenance personnel observed that a visible hole was developing in the side of the prefeeder structural frame. This prefeeder had been in regular service for approximately 3 years and operated normally.

Inspection of the lift assembly chain and double sprocket assembly on the operator side found that the double sprocket had moved outboard on its shaft, contacting the inside of the prefeeder frame. This action resulted in extensive contact damage to both the double sprocket and the frame. Maintenance personnel replaced the sprocket, bearings, and shaft and performed weld repairs to restore the integrity of the prefeeder frame.

Inspection of the lift assembly chain and double sprocket on the drive side found that the double sprocket on that side had also moved outboard by several inches but had not yet contacted the prefeeder frame; thus no damage had yet occurred. Maintenance personnel moved the sprocket back into the center position on the shaft and re-torqued the fasteners that secure the taper-lock bushings and double sprocket in the original position relative to the shaft.

Back to top

Recommended Action:

Alliance recommends that you perform an initial inspection as described below within 90 days after receipt of this service bulletin.

In addition, Alliance recommends that you perform a repeat inspection at annual intervals if the permanent spacer repair per step 4 is not accomplished.

Back to top

Procedure:

  1. De-energize and lock out the machine as described in the Operators Manual.

  2. Inspect the lift assembly chain double sprocket on both the operator side and the drive side for any evidence of sliding movement on the shaft. The sprocket is normally positioned on the shaft as indicated in Fig 1.

  3. If any relative movement is found, loosen the taper-lock bushing setscrews, re-position the double sprocket on the shaft, and tighten setscrews to 800 in-lbs. Refer to the attached Martin Taper Bushings instruction sheet. Use of Lock-tite on the setscrews is recommended.

  4. As a permanent repair operators can fabricate and install spacers on the shaft on both sides of the sprocket to prevent movement. Alliance can provide further details for spacer fabrication if prefeeder P# and shaft diameter are provided to Alliance.

  5. Note: If the permanent repair is installed there is no need to perform any repeat inspections as recommended above.

  6. Remove lock-outs and check for proper machine operation per the Operator’s Manual prior to resuming production.

Please advise Alliance of any significant findings resulting from your inspections. Comments may be forwarded to Mr. Mike Thayer, Customer Service Manager, at mthayer@alliancellc.net.

Figure 1: Double Sprocket Configuration

Back to top

Back to Index