Bulletin number: SB104 - A1
Category: Safety
Date issued: August 22, 2003
Machine models: TEI¨
Prefeeders manufactured prior to 1998
Back to Index
Refer to SB104 section 1 on page 2. Please do the following if
your extendo acme nut mount is a two-bolt design as shown in the
figure below:
 |
 |
Replace Part # 0015064
With 1023222 and
1023223 |
Replace Part # 0018546
With 1023451 and
1023416 |
Proper Four Bolt Mount |
Figure 1. Extendo Power Adjust Nut Retainer
Mounts
Replace the two bolt extendo
power adjust mount with a four bolt mount. The mount should be
installed with four grade 5, 3/8” UNC bolts and lock washers. The
Acme rod plastic nut fits inside the mount and the mount cover and
the mount are bolted to the extendo frame. Torque the bolts to 33
ft/lbs.
If you need assistance or would like to purchase replacement parts,
please call Gary Kneale, Field Service Manager, at 509-535-0356 and
select Option two.
Back to top